Source: Singapore Statutes Online | Archived by Legal Wires
| Rapid Transit Systems Act |
| Rapid Transit Systems (Creation of Rights) (No. 3) Notification 2004 |
|
| Citation and commencement |
| 1. This Notification may be cited as the Rapid Transit Systems (Creation of Rights) (No. 3) Notification 2004 and shall come into operation on 28th December 2004. |
| Powers of Authority |
| 2. The Authority or any person authorised by the Authority may, at any reasonable time and for the purposes of and incidental to the operation of the railway, enter upon the railway areas in the lands described in the First Schedule and exercise such rights as are described in the Second Schedule in, under or over those areas of land. |
| Inspection of plan |
| 3. A copy of the plan of the railway areas in the lands described in the First Schedule shall be available for inspection by the public free of charge at the office of the Land Transport Authority of Singapore at 1 Hampshire Road, Singapore 219428 between 9 a.m. and 5 p.m. from Mondays to Fridays (Saturdays, Sundays and public holidays excepted). |
| FIRST SCHEDULE |
| Paragraphs 2 and 3 and Second Schedule |
| Description of Land |
|
| THE SCHEDULE |
| Paragraph 2 |
1. The uninterrupted right to pass and repass with trains —
|
| 2. The right of uninterrupted passage without vehicles for the purpose of access and egress to and from any railway premises constructed on, above or under any of the lands described in the First Schedule or any other land adjoining thereto. |
| 3. The right at all times to have any structure constructed by the Authority on, above or under the lands described in the First Schedule for the operation of the Rapid Transit System supported, upheld and maintained by the soil and subsoil of such lands. |
Made this 23rd day of December 2004.
Chairman, Land Transport Authority of Singapore. |
| [LTA/LEG/LWX/RTSA.06; AG/LEG/SL/263A/2003/1 Vol. 2] |
Archived for legal research. Authoritative version at sso.agc.gov.sg.