| (a) | the electricity is generated by TPP’s generating unit in Lot 5160V in Mukim No. 7 at 92 Tuas South Avenue 3, Singapore 637368; |
| (b) | the electricity is transmitted to and consumed by the cooling water pumps 1 and 2 on the premises of the Public Utilities Board in Lot 5159T in Mukim No. 7 at 92 Tuas South Avenue 3, Singapore 637368; |
| (c) | the cooling water pumps 1 and 2 convey sea water to TPP’s generating unit mentioned in sub‑paragraph (a) for the purpose of cooling the generating unit; |
| (d) | TPP is a generation licensee; |
| (e) | TPP complies with any direction given by the Authority under section 17 of the Act in respect of the transmission of electricity. |