PART V | CONDITIONS RELATING TO CONSTRUCTION PERSONNEL |
17.—(1) For the purposes of this Part, unless the context otherwise requires —| “air-conditioning ducting installation” means the installation of air-conditioning ducting or any associated fittings, including thermal insulation, for the purposes of the cooling and mechanical ventilation of a building; [S 200/2011 wef 15/10/2011] |
| “cladding and curtain wall installation” means the installation of any external cladding or curtain wall, or any associated fittings, as the exterior covering or exterior wall of a building; [S 200/2011 wef 15/10/2011] |
| “construction personnel” has the same meaning as in section 29H(5) of the Act; [S 115/2013 wef 01/04/2013] |
“construction plant operation works” means operating any of the following plant or machinery:| (a) | a saddle jib tower crane; | | (b) | a luffing jib tower crane; | | (c) | a mobile crane (truck mounted); | | (d) | a crawler crane; | | (e) | a hydraulic excavator; | | (f) | a telescopic handler; | | (g) | bulldozer; | | (h) | a track shovel; | | (i) | an excavator loader; | | (j) | a piling rig; | | (k) | an underground pipe jacking machine; | | (l) | a tunnel boring machine; | | (m) | an asphalt concrete paver; | | (n) | a crawler drill; [S 200/2011 wef 15/10/2011] |
|
| “doors and windows installation” means the installation of any door, window panel or frame, or any associated fittings, for building works; [S 200/2011 wef 15/10/2011] |
| “drywall installation” means the on-site fabrication, installation or erection of any drywall panel or any associated fittings in the interior of a building; [S 200/2011 wef 15/10/2011] |
| “electrical works” means installing any wiring, cable, conduit, trunking, isolators, switch socket outlets, power switches or any other fittings for transmission of electricity for lighting, heating, cooling or other similar purposes in a building; |
| “fire protection works” has the same meaning as in the Fire Safety Act 1993; [S 200/2011 wef 15/10/2011] [S 416/2024 wef 31/12/2021] |
| “gas pipefitting works” means the installation of any gas service pipe, pipe fitting, conveyance, valve, regulator or any associated device used or to be used for the control and use of gas in a building; [S 200/2011 wef 15/10/2011] |
| “glazing works” means the installation of glass or any associated fittings in a building; [S 200/2011 wef 15/10/2011] |
| “joinery works” means the on-site fabrication of fitments, fittings or any related carpentry works for the installation of timber furniture to the interior wall, floor or any other part of a building; [S 200/2011 wef 15/10/2011] |
| [Deleted by S 416/2024 wef 15/06/2024] |
| “lift installation” means installation of any lift; [S 200/2011 wef 15/10/2011] |
| “man-year” means a period worked by a construction foreman or construction supervisor, as the case may be, comprising 260 working days; [S 115/2013 wef 01/04/2013] [S 786/2014 wef 01/01/2015] |
“mechanical and electrical works” —| (a) | means any work performed or carried out to install any mechanical or electrical installation; and | | (b) | includes the installing, constructing, erecting, repairing or the altering of the mechanical or electrical installation or the replacing of any part thereof or the adding of any part thereto or the carrying out of any work thereon for the maintenance thereof of such installation; but | | (c) | does not include work in relation to the manufacturing of such installation; [S 115/2013 wef 01/04/2013] |
|
| “plumbing and piping works” means installing any liquid, water or sanitary piping, or any associated fittings, including thermal insulation, for the conveyance of liquid, potable water distribution, or soil or waste water disposal in a building; [S 200/2011 wef 15/10/2011] |
| “rapid transit system” has the same meaning as in the Rapid Transit Systems Act 1995; [S 200/2011 wef 15/10/2011] [S 416/2024 wef 31/12/2021] |
“reinforced concrete works” means the on-site fabrication, installation or erection of formwork and steel reinforcement for reinforced concrete work, including —| (a) | fabrication (both on-site or off-site) of pre-cast concrete components; and | | (b) | installation of pre-cast concrete components; [S 115/2013 wef 01/04/2013] |
|
| “structural steel works” means the on-site fabrication, fitting, welding and erection of steel members or components to form an integral part of any structural system of a building; [S 200/2011 wef 15/10/2011] |
| “suspended ceiling installation” means the installation of any false ceiling, ceiling board, panel, tile or frame, or any associated fittings, that is hung from the soffit of structural elements of a building; [S 200/2011 wef 15/10/2011] |
| “tiling, stone laying and floor finishing works” means the laying of tiles, marble or stone finishes to any interior or exterior wall or any floor of a building, or timber finishes to any interior or exterior floor of a building; [S 200/2011 wef 15/10/2011] |
| “waterproofing works” means applying or laying of material to waterproof any basement, foundation, roof, wet area or wall in the interior or on the exterior of a building. |
| (2) Any reference in this Part to a class of registered construction personnel shall be a reference to the class in which the construction personnel is registered by the Authority under the Building and Construction Authority (Registration of Construction Personnel) Regulations 2008 (G.N. No. S 642/2008). |
|
| 18. [Deleted by S 786/2014 wef 01/01/2015] |
| Classes of work for definition of construction foreman |
| 19. The prescribed classes of work for the definition of “construction foreman” in section 29H(5) of the Act are the classes of work specified in Parts I, II and III of the Third Schedule. [S 416/2024 wef 15/06/2024] |
| Classes of construction supervisor for manpower programme |
| 19A. Only a construction supervisor who oversees the execution or performance of the classes of work specified in Part V or VI of the Third Schedule is a construction personnel who may be included in the manpower programme mentioned in regulation 20. [S 416/2024 wef 15/06/2024] |
20.—(1) For the purposes of section 29H(2) of the Act, the manpower programme for each significant general building work project in Singapore shall provide for registered construction personnel —| (a) | of such class as specified in paragraphs (3), (4) and (6); and [S 786/2014 wef 01/01/2015] | | (b) | of such number necessary to carry out the man-years of work computed in accordance with the formula specified in paragraph (2), rounded off to a maximum of 2 decimal points, |
| to be employed by or on behalf of the licensed general builder or engaged in connection with the significant general building work project. |
(2) For the purposes of this regulation —| (a) | in the case where the value of a significant building work project does not exceed $100 million, the formula referred to in paragraph (1)(b) shall be — | | is the manpower factor specified in paragraphs (3), (4) and (6); |
| | | is the value of the significant building work project; and |
| | | is the value of $10 million; and |
|
|
[S 786/2014 wef 01/01/2015] | | (b) | in the case where the value of a significant building work project exceeds $100 million, the formula referred to in paragraph (1)(b) shall be — | | is the manpower factor specified in paragraphs (3), (4) and (6); |
| | | is the value of the significant building work project; and |
| | | is the value of $20 million. |
|
|
[S 786/2014 wef 01/01/2015] |
|
(3) Where the significant general building work project involves addition, alteration or repair works to an existing building not described in paragraph (4) —| (a) | in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1; | | (b) | in the case of any class of work specified in Part II or III of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1; [S 115/2013 wef 01/04/2013] | | (c) | [Deleted by S 786/2014 wef 01/01/2015] | | (d) | [Deleted by S 786/2014 wef 01/01/2015] | | (e) | in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25; and [S 115/2013 wef 01/04/2013] | | (f) | in the case of any class of work specified in Part VI of the Third Schedule or any combination thereof, the number of construction supervisors in any such class or classes of work shall be determined using the manpower factor of 0.25. [S 115/2013 wef 01/04/2013] [S 786/2014 wef 01/01/2015] |
|
(4) Where the significant general building work project involves erecting, or any addition, alteration or repair works to, any flyover, bridge, tunnel or other structure similar thereto and is not a significant general building work project involving the construction of a station or depot of a rapid transit system —| (a) | in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 0.75; and [S 115/2013 wef 01/04/2013] [S 786/2014 wef 01/01/2015] | | (b) | [Deleted by S 786/2014 wef 01/01/2015] | | (c) | in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25. [S 115/2013 wef 01/04/2013] [S 786/2014 wef 01/01/2015] |
|
| (5) [Deleted by S 786/2014 wef 01/01/2015] |
(6) In the case of any other significant general building work project not specified in paragraph (3) or (4) —| (a) | in the case of any class of work specified in Part I of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1; | | (b) | in the case of any class of work specified in Part II or III of the Third Schedule or any combination thereof, the number of construction foremen in any such class or classes of work shall be determined using the manpower factor of 1; [S 115/2013 wef 01/04/2013] | | (c) | [Deleted by S 786/2014 wef 01/01/2015] | | (d) | [Deleted by S 786/2014 wef 01/01/2015] | | (e) | [Deleted by S 786/2014 wef 01/01/2015] | | (f) | in the case of the class of work specified in Part V of the Third Schedule, the number of construction supervisors shall be determined using the manpower factor of 0.25; and [S 115/2013 wef 01/04/2013] | | (g) | in the case of any class of work specified in Part VI of the Third Schedule or any combination thereof, the number of construction supervisors in any such class or classes of work shall be determined using the manpower factor of 0.25. [S 200/2011 wef 15/10/2011] [S 115/2013 wef 01/04/2013] [S 786/2014 wef 01/01/2015] |
|
|
| Lodgment of manpower programme |
20A.—(1) Subject to regulation 20B(3), the builder holding a Class 1 general builder’s licence shall, in respect of each significant general building work project to be undertaken in Singapore by that builder on or after 16th June 2009, lodge with the Commissioner a manpower programme that satisfies the requirements in regulation 20 no later than the 30th day after the grant of the permit under section 6 of the Act to carry out structural works in that significant general building work project.(2) Every manpower programme lodged under paragraph (1) by a builder holding a Class 1 general builder’s licence must —| (a) | specify the significant general building work project to which it relates; | | (b) | contain the following details and particulars about the registered construction personnel to be employed by or on behalf of the builder, or to be engaged, in connection with the significant general building work project:| (i) | the class or classes of registered construction personnel and the class or classes of work according to their registration under the Building and Construction Authority (Registration of Construction Personnel) Regulations 2008 (G.N. No. S 642/2008); | | (ii) | the number or proportion of the registered construction personnel in each such class of work; | | (iii) | the period each registered construction personnel is to be so employed or so engaged in connection with the significant general building work project; and | | (iv) | such other details and particulars relating to the contents of the particular manpower programme as the Commissioner may require. |
|
|
(3) Every manpower programme lodged under paragraph (1) must be in the form that —| (a) | is provided by the Authority and obtainable from the Building and Construction Authority Academy at 200, Braddell Road, Singapore 579700 during such hours as that office is open for business; or | | (b) | is set out on the Authority’s Internet website http://www.bca.gov.sg/coretrade/submission. |
|
| (4) The Commissioner may permit manpower programmes to be lodged by any means, including electronic means, that he thinks fit. |
| (5) Where the Commissioner accepts the lodgment of a manpower programme by a builder (including any fresh manpower programme referred to in regulation 20B(3)), he must as soon as practicable give notice of his acceptance in writing to the builder. |
| (6) A manpower programme in respect of any significant general building work project may be regarded as lodged only when accepted by the Commissioner in the manner set out in paragraph (5). [S 274/2009 wef 16/06/2009] |
|
20B.—(1) The Commissioner may refuse to accept the lodgment of any manpower programme that —| (a) | is incomplete; | | (b) | is not in the form approved by the Commissioner; or | | (c) | is apparent does not comply with or was not lodged in accordance with the provisions of these Regulations. |
| (2) Upon refusing to accept the lodgment of any manpower programme (including any fresh manpower programme referred to in paragraph (3)), the Commissioner must by notice in writing as soon as practicable inform the builder concerned of his refusal and give his reasons for refusing the lodgment. |
| (3) A builder whose lodgment of a manpower programme in respect of a significant general building work project to be undertaken in Singapore by the builder is refused under this regulation must, no later than the 7th day after receiving the notice of refusal under paragraph (2), or within such further period as the Commissioner allows in any particular case, re-lodge a fresh manpower programme that is in respect of the same significant general building work project and that satisfies the requirements in regulations 20 and 20A(2) and (3). [S 274/2009 wef 16/06/2009] |
|
| Updates and changes in lodged manpower programme |
20C.—(1) After a manpower programme is lodged by a builder under regulation 20A(1) in respect of any particular significant general building work project, the builder must, at any time before deploying any registered construction personnel (whether employed by or on behalf of the builder or engaged) to work in connection with the significant general building work project, lodge with the Commissioner an update by way of a notice containing the following:| (a) | the names of each of the registered construction personnel; and | | (b) | the number and other particulars of the certificate of registration issued to each of the registered construction personnel under the Building and Construction Authority (Registration of Construction Personnel) Regulations 2008 (G.N. No. S 642/2008). |
(2) For the purposes of section 29H(3) of the Act, if any of the following changes occur after a manpower programme is lodged by a builder under regulation 20A(1) in respect of any particular significant general building work project, the builder must, within a period of 7 days after that change, lodge with the Commissioner a notice describing the change:| (a) | a change in the number or proportion of registered construction personnel specified in the manpower programme, whether the change occurs with respect to any class of registered construction personnel or in any class of work of such registered construction personnel; | | (b) | a change in any particular registered construction personnel whose name and particulars are specified in the update notice under paragraph (1); | | (c) | a change in the period specified in the manpower programme that any registered construction personnel is to be employed by or on behalf of the builder, or to be engaged, in connection with that particular significant building work project; | | (d) | a change in the value of the significant general building work project, or in its expected date of completion, as specified in the manpower programme; | | (e) | a change in any other details or particulars in the manpower programme referred to in regulation 20A(2)(b)(iv). |
|
(3) Every notice to the Commissioner under paragraph (1) or (2) must be in the form that —| (a) | is provided by the Authority and obtainable from the Building and Construction Authority Academy at 200, Braddell Road, Singapore 579700 during such hours as that office is open for business; or | | (b) | is set out on the Authority’s Internet website http://www.bca.gov.sg/coretrade/submission. |
|
| (4) The Commissioner may permit any notice under paragraph (1) or (2) to be lodged by any means, including electronic means, that he thinks fit. [S 274/2009 wef 16/06/2009] |
|
| Steps to ensure compliance with manpower programme |
20D. For the purposes of section 29H(1)(b) and (4) of the Act, if a builder who undertakes a significant general building work project in Singapore fails to keep and maintain at every site of the significant general building work project —| (a) | a copy of the manpower programme lodged in respect of that project, as updated by any notice lodged under regulation 20C(1) or (2), in connection with that significant general building work project; | | (b) | a record of daily attendance for all registered construction personnel employed by or on the builder’s behalf or engaged in connection with that significant general building work project (including the times of arrival and departure of each registered construction personnel at the site) in the form approved by the Commissioner; and | | (c) | a record of the grounds of excuse or other causes for every occasion that any of those registered construction personnel fail to attend work at the site (including the days of leave he may be entitled to and sick leave), |
| he shall not be regarded as taking all practicable steps to ensure that those registered construction personnel are in compliance with the manpower programme lodged in respect of that significant general building work project. |
[S 274/2009 wef 16/06/2009] |
| Furnishing information, etc. |
20E.—(1) The Commissioner, or a person appointed by him for this purpose, may by written notice require any builder holding a Class 1 general builder’s licence and undertaking a significant general building work project in Singapore to furnish, within a reasonable period specified in the notice (being not less than 3 days), and in such form and manner as may be specified in the notice —| (a) | the record of daily attendance referred to in regulation 20D(b); | | (b) | the record of the grounds of excuse or other causes for non-attendance referred to in regulation 20D(c); and | | (c) | such other documents and information relating to any matter which the Commissioner considers necessary to administer this Part and section 29H of the Act, which are within the knowledge of that builder or in his custody or under his control. |
(2) The power to require a person to furnish any document or information under paragraph (1) includes the power —| (a) | to require that person, or any person who is or was an officer or employee of his, to provide an explanation of the document or information; and | | (b) | if the information is recorded otherwise than in legible form, to require the information to be made available to the Commissioner or authorised officer in legible form. |
|
| (3) Any person who, without reasonable excuse, fails to do anything required of him by notice under paragraph (1) shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $10,000. |
(4) Any person who —| (a) | intentionally alters, suppresses or destroys any document or information which he has been required by a notice under paragraph (1) to furnish; or | | (b) | in furnishing any document or information required under paragraph (1), makes any statement which he knows to be false in a material particular or recklessly makes such a statement, |
| shall be guilty of an offence and shall be liable on conviction to a fine not exceeding $10,000 or to imprisonment for a term not exceeding 12 months or to both. |
[S 274/2009 wef 16/06/2009] |
|
|